Project – Tor View School – Multi Use Building

Summary:

Architect – AHR Building Consultancy
Contract sum – £1,400,000.00
Commencement date – June 2024
Completion date – April 2025
Contract duration – 10 months

Project Overview:

This project was named a multi-use space which was designed and built to be used as the school’s sports hall; incorporating a hidden sunken trampoline and a hall for school performances and presentations with retractable seating.

The project was completed on time and within budget with no health and safety issues on site.

This project consisted of a large steel frame on a piled and vibro-compacted slab. The cladding was a mix of Kalzip standing seam and fibre cement rainscreen. The site was very compact and access was gained by means of a temporary entrance and roadway across the school playing field.